update......ROAD WORK ADVISORY – Sharon Hollow Road

Sharon Hollow Rd Resurfacing 
Project Update #1

Milling, Milling, Milling...

May 7, 2024

Our resurfacing project on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester and Sharon Townships is going well.  

Yesterday, the contractor was able to mill the existing road surface. Today, the expected rain will pause operations. On Wednesday, May 8, 2024, the contractor expects to begin paving the new road surface, which can take approximately two days to complete, pending weather conditions. Once paving is finished, aggregate (stone) shoulders and pavement markings will be placed.  

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.  

Have questions about the project? Contact Mike Bernbeck, Project Manager – Design & Construction, at (734) 327-6654, or via email at bernbeckm@wcroads.org.